Workshop noise doesn't have to be a fact of life
Machines, impacts, forklifts, metal walls: in a workshop, sound reflects off every surface and adds to the direct noise of the workstations. It is this reflected part that can be eliminated.
You don't make a machine silent by treating the walls. You remove the reverberant field, meaning all the noise that isn't the machine you're working at.
Three reasons to act
The 85 dB threshold
In France, from 85 dB(A) over 8 hours, the employer must implement a noise reduction programme. Acoustic correction of the room is the first lever, before personal protection.
Understood without shouting
Safety instructions, alarms, communication between operators: in an overly reverberant room, intelligibility drops, and safety with it.
A site in operation
Our objects hang from existing structures, roof framing or cable trays, without stopping production or altering the building.
Avant, après, mesuré
320 m² workshop, steel frame, metal cladding. 22 suspended clouds in two layers.
Before, after
Reverberation time according to the Sabine model. Results vary with volume, materials and use; validated on site by before / after measurement.
What French regulations require
- Regulatory action threshold (France)
- 85 dB(A) over 8 h
- Exposure limit value
- 87 dB(A) over 8 h
- Target spatial sound decay
- DL2 ≥ 3 dB
- Workshop, technical room
- RT ≤ 1.5 s
- Reference (France)
- French Labour Code, art. R4431-1 et seq.
Premises that need treatment?
On-site exposure measurement, treatment sizing, check after installation. Without stopping production.